– You create a task and put an estimate: 5h
– Assign hours 1h (left 4h)
– You create a subtask of the father
– Assignments 2h (they are still 4h)
– Then you will have that it does not add well the estimated original hours.
…
Look at this: … there is basically no solution currently.
Atlassian recommends this … story points and measure speed
If you want the subject of the Subtasks Estimates to be added, please vote for this ticket:
– https://jira.atlassian.com/browse/JSWSERVER-9167
By MrAddon